KIRTHAI HEP - II
Kirthai-II HE Project is a run-of- river project located in Kishtwar district, J&K at about 25 Kms upstream of Kiru H.E. Project on river Chenab. The project would provide an annual generation of 3329.52 MU in a 90% dependable year.
Feature List
Feature Name |
Description |
Approach |
Nearest rail head: Udhampur – 180 KM
Nearest Airport : Jammu – 240 KM
|
Location |
District Kisthwar, UT of Jammu & Kashmir |
Capacity |
930 MW (6X140+2X35+2X10) |
Design Energy |
3329.52 MUs (in a 90% dependable year) |
Date of Commercial Operation (COD) |
60 Months |
Estimated Project Cost |
₹ 6384.39 Crore at February 2020 Price level |
River |
CHENAB |
TECHNICAL FEATURES- The structures required to be constructed for Kirthai-II HE Project are:
HRT | 1 no., 11m diameter, 5.79 km length |
Dam | 131m (H) , Concrete Gravity |
Surge Shaft | 22.5 m dia. & 97.0 m height |
Pressure Shaft | 2 No., 6.6 m 310m length each |
Power House | Underground (6X140+2X35+2X10) |
Project Status | Under Clearance |