Name of Project State/UT Installed Capacity(MW) Total Capacity(MW) Status
Teesta - IV HEP Sikkim 4 * 125 520 Awaiting Clearances
600 MW Solar Power Project Khavda, Gujarat (Stage-II)( Under1000 MW CPSUs Scheme ) Gujarat 600 600 Under Construction
Teesta VI HEP Sikkim 4*125 500 Under Construction
Indira Sagar (JV) Madhya Pradesh 8 * 125 1000 Commissioned
Omkareshwar (JV) Madhya Pradesh 8 * 65 520 Power Station
Kalpi Solar Power Project (BSUL) 65 MW Uttar Pradesh 65 MW 65 MW Commissioned
Kwar HEP (JV) UT of Jammu and Kashmir 4 * 135 540 Under Construction
Kirthai HEP - II UT of J&K 930 MW 930 MW Awaiting Clearances
Rangit-IV HEP (JV) Sikkim 3 * 40 120 Under Construction
Ratle HEP (JV) UT of Jammu and Kashmir 850 850 Under Construction
200 MW Grid connected solar PV Project (600 MW Solar park at Khavda ) Stage - III Gujarat 200 MW 200 MW Under Construction
Pakal Dul (JV) UT of Jammu and Kashmir 4 * 250 1000 Under Construction
Kiru HEP (JV) UT of Jammu and Kashmir 4 * 156 624 Under Construction
Total 7469 MW