|
Garba Tawaghat
| Uttarakhand |
630 |
630 |
Under Survey and Investigation Stage |
|
Uri-I HEP (Stage-II)
| UT of Jammu and Kashmir |
240 |
240 |
Awaiting Clearances |
|
Dulhasti (Stage-II)
| UT of Jammu and Kashmir |
260 MW |
260 MW |
Awaiting Clearances |
|
Teesta - IV HEP
| Sikkim |
4 * 125 |
520 |
Awaiting Clearances |
|
Dugar HEP
| Himachal Pradesh |
500 |
500 |
Awaiting Clearances |
|
Kalpong
| Andaman and Nicobar |
1 * 5.25 |
5.25 |
Commissioned |
|
Sippi
| Arunachal Pradesh |
2 * 2 |
4 |
Commissioned |
|
Kambang
| Arunachal Pradesh |
3 * 2 |
6 |
Commissioned |
|
Kurichu
| Bhutan |
15*4 |
60 |
Commissioned |
|
Devighat
| Nepal |
1*14 |
14 |
Commissioned |
|
Phukot Karnali
| Nepal |
480 |
480 |
Overseas Projects |
|
West Seti 800MW
| Nepal |
800 |
800 |
Overseas Projects |
|
SR 6
| Nepal |
460 |
460 |
Under Survey and Investigation Stage |
|
Kamala HEP
| Arunacahal Pradesh |
1720 |
1720 |
Awaiting Clearances |
|
Subansiri Upper HEP
| Arunacahal Pradesh |
1605 |
1605 |
Awaiting Clearances |
|
Mirzapur Solar Project (BSUL, JV with UPNEDA)
| Uttar Pradesh |
100 |
100 |
Awaiting Clearances |
|
Madhogarh Solar Project (BSUL, JV with UPNEDA)
| Uttar Pradesh |
45 |
45 |
Awaiting Clearances |
|
Jalaun Ultra Mega Solar Park 1200 MW (BSUL, JV with UPNEDA)
| Uttar Pradesh |
|
|
Under Construction |
|
Under1000 MW CPSUs Scheme Solar Project, Rajasthan 300 MW
| Rajasthan |
|
|
Power Station |
|
Indirasagar - Omkareshwar Pumped Storage Project (On Stream)
| Madhya Pradesh |
640 |
640 |
Under Survey and Investigation Stage |
|
Savitri PSP
| Maharashtra |
2400 |
2400 |
Under Survey and Investigation Stage |
|
Gadikota
| Andhra Pradesh |
1200 |
1200 |
Under Survey and Investigation Stage |
|
Yaganti
| Andhra Pradesh |
1000 |
1000 |
Under Survey and Investigation Stage |
|
West Seti (Nepal)
| Nepal |
800 |
800 |
Under Survey and Investigation Stage |
|
SR 6.
| |
460 |
460 |
Overseas Projects |
|
Masinta PSP
| Odisha |
1000 |
1000 |
Under Survey and Investigation Stage |
|
Kuppa PSP
| Gujarat |
900 |
900 |
Under Survey and Investigation Stage |
|
KALU PSP
| Maharashtra |
1800 |
1800 |
Under Survey and Investigation Stage |
|
Teesta VI HEP
| Sikkim |
4*125 |
500 |
Under Construction |
|
200 MW Grid connected solar PV Project (600 MW Solar park at Khavda) Stage-I
| Gujarat |
200 |
200 |
Under Construction |
|
Under1000 MW CPSUs Scheme Solar Project, Rajasthan 300 MW P S
| Rajasthan |
300 MW |
300 MW |
Power Station |
|
Baira Siul
| Himachal Pradesh |
3 * 60 |
180 |
Power Station |
|
Loktak
| Manipur |
3 * 35 |
105 |
Power Station |
|
Salal
| UT of Jammu & Kashmir |
6 * 115 |
690 |
Power Station |
|
Tanakpur
| Uttarakhand |
94.2 |
94.2 |
Power Station |
|
Chamera - I
| Himachal Pradesh |
3 * 180 |
540 |
Power Station |
|
Uri - I
| UT of Jammu & Kashmir |
4 * 120 |
480 |
Power Station |
|
Rangit
| Sikkim |
3 * 20 |
60 |
Power Station |
|
Chamera - II
| Himachal Pradesh |
3 * 100 |
300 |
Power Station |
|
Indira Sagar (JV)
| Madhya Pradesh |
8 * 125 |
1000 |
Commissioned |
|
Dhauliganga
| Uttarakhand |
4 * 70 |
280 |
Power Station |
|
Dulhasti
| UT of Jammu & Kashmir |
3 * 130 |
390 |
Power Station |
|
Omkareshwar (JV)
| Madhya Pradesh |
8 * 65 |
520 |
Power Station |
|
Teesta - V
| Sikkim |
3 * 170 |
510 |
Power Station |
|
Sewa - II
| UT of Jammu & Kashmir |
3 * 40 |
120 |
Power Station |
|
Chamera-III
| Himachal Pradesh |
3 * 77 |
231 |
Power Station |
|
Teesta Low Dam - III
| West Bengal |
4 * 33 |
132 |
Power Station |
|
Nimmo-Bazgo
| UT of Ladakh |
3 * 15 |
45 |
Power Station |
|
Chutak
| UT of Ladakh |
4 * 11 |
44 |
Power Station |
|
Parbati - III
| Himachal Pradesh |
4 * 130 |
520 |
Power Station |
|
Uri-II
| UT of Jammu & Kashmir |
4 * 60 |
240 |
Power Station |
|
Teesta Low Dam - IV
| West Bengal |
4 * 40 |
160 |
Power Station |
|
Jaisalmer (Wind Power)
| Rajasthan |
50 |
50 |
Power Station |
|
Solar Power
| Tamil Nadu |
50 |
50 |
Commissioned |
|
Kishanganga HEP
| UT of Jammu & Kashmir |
3 * 110 |
330 |
Power Station |
|
Floating Solar Power Project ( In the reservoir of Omkareshwar Project) - NHDC
| Madhya Pradesh |
88 |
88 |
Power Station |
|
Kalpi Solar Power Project (BSUL) 65 MW
| Uttar Pradesh |
65 MW |
65 MW |
Commissioned |
|
Sanchi Solar Power Project
| Madhya Pradesh |
08 MW |
08 MW |
Commissioned |
|
Parbati - II
| Himachal Pradesh |
4 * 200 |
800 |
Power Station |
|
Solar Power
| Tamil Nadu |
50 |
50 |
Power Station |
|
Wind
| Rajasthan |
50 |
50 |
Power Station |
|
Kirthai HEP - II
| UT of J&K |
820 MW |
820 MW |
Awaiting Clearances |
|
Sawalkot HEP
| UT of Jammu and Kashmir |
1856 |
1856 |
Awaiting Clearances |
|
Rangit-IV HEP (JV)
| Sikkim |
3 * 40 |
120 |
Under Construction |
|
Ground Mounted Solar Power Project in Central University of Rajasthan, Ajmer
| Rajasthan |
0.70 |
0.70 |
Joint Venture |
|
Ratle HEP (JV)
| UT of Jammu and Kashmir |
850 |
850 |
Under Construction |
|
Pakal Dul (JV)
| UT of Jammu and Kashmir |
4 * 250 |
1000 |
Under Construction |
|
Kiru HEP (JV)
| UT of Jammu and Kashmir |
4 * 156 |
624 |
Under Construction |
|
Dibang
| Arunachal Pradesh |
12 * 240 |
2880 |
Awaiting Clearances |
|
Kwar HEP (JV)
| UT of Jammu and Kashmir |
4 * 135 |
540 |
Under Construction |
|
Floating Solar Power Project, West Kallad
| kerala |
50 |
50 |
Under Construction |
|
Under1000 MW CPSUs Scheme Solar Project, Andhra Pradesh 100 MW
| Andhra Pradesh |
100 |
100 |
Under Construction |
|
Ground Mounted Solar Power Project, Ganjam
| Odisha |
40 |
40 |
Under Construction |
|
200 MW Grid connected solar PV Project (600 MW Solar park at Khavda ) Stage - III
| Gujarat |
200 MW |
200 MW |
Under Construction |
|
Subansiri (Lower)
| Arunachal Pradesh and Assam |
8 * 250 |
2000 |
Under Construction |
|
600 MW Solar Power Project Khavda, Gujarat (Stage-II)( Under1000 MW CPSUs Scheme )
| Gujarat |
600 |
600 |
Under Construction |
|
Roof Top Solar
| Various NHPC Locations |
3.29 |
3.29 |
Under Construction |
|
Total |
38464 MW |
|