Kirthai HEP - II
Kirthai-II HE Project is a run-of- river project located in Kishtwar district, J&K at about 25 Kms upstream of Kiru H.E. Project on river Chenab. The project would provide an annual generation of 3329.52 MU in a 90% dependable year.
| Feature Name | Description |
|---|---|
| Approach | Nearest rail head: Udhampur – 180 KM Nearest Airport : Jammu – 240 KM |
| Location | District Kisthwar, UT of Jammu & Kashmir |
| Capacity | 930 MW (6X140+2X35+2X10) |
| Design Energy | 3329.52 MUs (in a 90% dependable year) |
| Date of Commercial Operation (COD) | 60 Months |
| Estimated Project Cost | ₹ 6384.39 Crore at February 2020 Price level |
| River | CHENAB |
TECHNICAL FEATURES
- The structures required to be constructed for Kirthai-II HE Project are:
| HRT | 1 no., 11m diameter, 5.79 km length |
| Dam | 131m (H) , Concrete Gravity |
| Surge Shaft | 22.5 m dia. & 97.0 m height |
| Pressure Shaft | 2 No., 6.6 m 310m length each |
| Power House | Underground (6X140+2X35+2X10) |
| Project Status | Under Clearance |