200 MW GRID CONNECTED SOLAR PV PROJECT (600 MW SOLAR PARK AT KHAVDA) STAGE-I
Project Brief:
On 3rd May’2023, NHPC bagged 200 MW Grid Connected Solar photovoltaic Power Projects located in 600 MW Solar Park at Khavda, Gujarat @ Rs 2.73 per unit through Tariff based competitive bidding from GUVNL. NHPC received LOI (Letter of intent) from GUVNL on 16th May’2023 for setting up of 200 MW SPV Projects at solar park. PPA signed between NHPC and GUVNL on 09.08.2023. LOA for EPC Contract issued by NHPC to M/s Apollo Green energy limited on 05.08.2024. Survey works and Design & Engineering is in progress.
On 3rd May’2023, NHPC bagged 200 MW Grid Connected Solar photovoltaic Power Projects located in 600 MW Solar Park at Khavda, Gujarat @ Rs 2.73 per unit through Tariff based competitive bidding from GUVNL. NHPC received LOI (Letter of intent) from GUVNL on 16th May’2023 for setting up of 200 MW SPV Projects at solar park. PPA signed between NHPC and GUVNL on 09.08.2023. LOA for EPC Contract issued by NHPC to M/s Apollo Green energy limited on 05.08.2024. Survey works and Design & Engineering is in progress.
Feature Name | Description |
---|---|
Location | Village: Khavda RE Park, District- Kutch, Gujarat |
Approach | Nearest Railhead: Bhuj (Appx. 110 KM), Nearest Airport: Bhuj (Appx. 110 KM) |
Capacity | 200 MW (AC) |
Design Energy | 494 MU (CUF 28.20%) |
Project Cost | Rs. 929 Crs (inclusive of 05 yrs O&M Charges) |
Date of Commercial Operation (COD) | 20.08.2025 (Anticipated) |
Technical Features:
Project Capacity: 200 MW
Connectivity Substation: Inside GSEC’s RE Park at Khavda, Gujarat
Voltage level of Transmission line: 400 kV
Annual Generation for 1st Year: 494 MU (CUF 28.20%)
Project Status : Under Construction
Project Capacity: 200 MW
Connectivity Substation: Inside GSEC’s RE Park at Khavda, Gujarat
Voltage level of Transmission line: 400 kV
Annual Generation for 1st Year: 494 MU (CUF 28.20%)
Project Status : Under Construction