Kwar HEP (JV)
Kwar Hydro Electric Project (540 MW) is proposed on River Chenab, located in Kishtwar district of the Jammu & Kashmir. The project is envisaged as a Run of River Scheme
Feature List
Feature Name
Description
Location
Village Padyarna in district Kishtwar of Jammu & Kashmir.
Approach
Nearest Railhead – Udhampur (190 Km) Nearest Airport – Jammu (270 Km)
River
Chenab
Capacity
540 MW (4 x 135 MW)
Design Energy
1975.54 MU (in a 90% dependable year)
Estimated Project Cost
Rs. 4526.12 crore( Sep'2020 Price Level)
Date of Commercial Operation (COD)
DEC 2027
TECHNICAL FEATURES Dam Concrete gravity dam (109 m high, 195 m long) Diversion Tunnel 1 nos, Length 686 m, 9.5m dia, Horse Shoe Shaped Water Conductor System 04 nos., 5.650 m dia underground circular steel lined Pressure Shafts. Pressure Shaft / Penstock 4 Nos., 5.65 m dia, Underground Circular steel lined Power House Underground, 4 Units, size 140 m x 23.3 m x 50 m TRT 2 nos. 9.5 m dia Horse Shoe shaped, concrete line TRT’s of lengths 2786m and 2963m. Rated Head 103.1 m Project Status Under Construction