Kiru HEP (JV) - NHPC India
Kiru HEP (JV) - NHPC India
Kiru HEP (JV)
Kiru Hydro Electric Project (624 MW) is proposed on River Chenab, located in Kishtwar district of Jammu & Kashmir. The project is envisaged as a Run of River Scheme.
Feature List
Feature Name
Description
Location
Village Kiru / Pathrnakki in district Kishtwar of Union Territory of Jammu & Kashmir
Approach
Nearest Railhead – Udhampur (220 Km) Nearest Airport – Jammu (280Km)
River
Chenab
Capacity
624 MW (4 x 156 MW)
Design Energy
2272.04 MU (in a 90% dependable year)
Estimated Project Cost
Rs. 4287.59 crore (July. 2018 Price Level)
Date of Commercial Operation (COD)
SEP-2026 (Anticipated)
TECHNICAL FEATURES Dam Concrete gravity dam (135 m high, 193 m long) Diversion Tunnel 1 nos, Length 700m, 9m dia, Horse Shoe Shaped Water Conductor System Under ground Circular steel lined, 4 Nos., Dia : 5.5 m (internal) and length varying from 316m to 322m. Pressure Shaft / Penstock 4 Nos., 5.5 m dia, Underground Circular steel lined, 316 m to 322 m length Power House Underground, 4 Units, size 182 m x 23.6 m x 51.2 m TRT 4 nos. 7 m dia Horse Shoe shaped, varies length from 165 m to 190 m Rated Head 117.98 m Project Status Under Construction