Parbati - III


| Feature Name | Description |
|---|---|
| Approach | 1) Nearest Rail Head :- Kiratpur which is 190 Km away 2) Nearest Airport: - Bhuntar which is 36 Km away 3) 508 Km away from Delhi 4) 258 Km away from Chandigarh 5) 208 km away from Shimla |
| Location | Behali village in Kullu district of Himachal Pradesh |
| Capacity | 520 MW (4 x 130 MW) |
| Design Energy | 1963.29 MU |
| Beneficiary States/UTs | Uttrakhand, U.P., Delhi, H.P., Haryana, J&K, Punjab, Rajasthan & Chandigarh |
| Date of Commercial Operation (COD) | U#-I 24 March 2014; U#-II 24 March 2014; U#-III 30 March 2014; U#-IV 06 June 2014 |
| Dam | |
| Type | Rock fill |
| Height | 43 m |
| FRL MDDL | EL 1330.00 m EL 1314.00 m |
| HRT | |
| Shape | Horse Shoe |
| Length | 7875 m |
| Diameter | 7.25 m |
| Penstock | |
| Diameter | 3 m |
| TRT | |
| Shape Length Diameter | Horse Shoe 2713 m 8.1 m |
| Power House | |
| Type | Underground power house |
| Capacity | Comprising of 4 units of 130 MW each |
| Turbine | |
| Type | Francis |
| Rated Head | 326 m |
| Design Discharge | 44.3 m3/s |
| No. of GV | 20 |
| Generator | |
| Rated continuous output | 145 MVA |
| Rated Voltage | 1 3.8 kV |
| No of Poles | 18 |
| Rated Speed | 333.33 rpm |
| Generator Step up Transformer: (GSU) | |
| Type | 1-Ф |
| Voltage Ratio | 13.8 / 400 /√(3 ) kV |
| MVA Rating | 53 MVA |
| Type of cooling | OFWF |
| Switchyard /Potyard | |
| Switchyard /Potyard | GIS (Gas Insulated Switchgear) |
| Voltage level | 420 kV |
| No. of lines | 02 Nos. |
| 400 kV Line -I : Parbati-III to 400 kV Pooling Station Banala | |
| 400 kV Line-II: Parbati-III-Sainj HE Project- Parbat-II HE Project - 400 kV Pooling Station Banala ( Orginal Scheme). |