600 MW SOLAR POWER PROJECT KHAVDA, GUJARAT (STAGE-II)( UNDER1000 MW CPSUS SCHEME )
Project Brief:
600 MW Solar Power Project at Khavda, Gujarat is being set up under Ministry of New and Renewable Energy (Govt. of India) CPSU Scheme, Phase-II, Tranche-III. NHPC is implementing the development of this project through EPC Contract for 600 MW Grid Connected Solar PV Project and transmission line for power evacuation to ISTS sub-station along with comprehensive O&M for 05 years. The power generated from this 600 MW project shall be evacuated through KPS-III ISTS Substation for use by Government/Government entities through sale of power of 500 MW to Southern Power Distribution Company of Telangana & Northern Power Distribution Company of Telangana & 100 MW to Punjab State Power Corporation Limited (PSPCL) . Only domestically manufactured Cells & Modules shall be used for setting up of Solar Plant as per the provision of CPSU Scheme.
600 MW Solar Power Project at Khavda, Gujarat is being set up under Ministry of New and Renewable Energy (Govt. of India) CPSU Scheme, Phase-II, Tranche-III. NHPC is implementing the development of this project through EPC Contract for 600 MW Grid Connected Solar PV Project and transmission line for power evacuation to ISTS sub-station along with comprehensive O&M for 05 years. The power generated from this 600 MW project shall be evacuated through KPS-III ISTS Substation for use by Government/Government entities through sale of power of 500 MW to Southern Power Distribution Company of Telangana & Northern Power Distribution Company of Telangana & 100 MW to Punjab State Power Corporation Limited (PSPCL) . Only domestically manufactured Cells & Modules shall be used for setting up of Solar Plant as per the provision of CPSU Scheme.
Feature Name | Description |
---|---|
Location | Village: Khavda RE Park, District- Kutch, Gujarat |
Approach | Nearest Railhead: Bhuj (Appx. 110 KM), Nearest Airport: Bhuj (Appx. 110 KM) |
Capacity | 600 MW (AC) |
Design Energy | 1766.55 MU (CUF: 33.59%) |
Date of Commercial Operation (COD) | 02.03.2026 (Anticipated) |
Project Cost | Rs. 4295.6 Crs (inclusive of 05 yrs O&M Charges) |
Technical Features:
Project Capacity: 600 MW
Connectivity Substation: KPS-III Substation
Voltage level of Transmission line: 400 kV
Length of O/H Transmission line: 15 KM
Annual Generation for 1st Year: 1766.55 MU (CUF: 33.59%)
DC:AC Ratio: 1.5
Project Status : Under Construction
Project Capacity: 600 MW
Connectivity Substation: KPS-III Substation
Voltage level of Transmission line: 400 kV
Length of O/H Transmission line: 15 KM
Annual Generation for 1st Year: 1766.55 MU (CUF: 33.59%)
DC:AC Ratio: 1.5
Project Status : Under Construction