|
Annual
Review 2005-06
Highest ever turnover and
net profit, Commissioning of 280 MW Dhauliganga Power Station in
Uttaranchal, finalizing major contract agreements for civil
works of Uri-II, Chamera-III, Parbati-III & Teesta Low Dam
Stage-IV, surpassing the MOU generation target, achieving 98.16
% Capacity Index, record realization of energy bills from
various beneficiaries, signing of power purchase agreements for
7 projects with various beneficiaries, Bagging more consultancy
assignments, Obtaining Government sanction for 4 projects with a
total installed capacity of 1151 MW, bagging 2 projects in
Sikkim and 3 projects in Uttaranchal, Submission of DPR of 8
Projects with an installed capacity of 6085 MW to CEA/ CWC for
TEC / TEA, speeding up construction activities on Dul Hasti,
Teesta Stage-V and other Projects are some of the major
achievements of NHPC during the Financial Year 2005-06.
FINANCIAL INITIATIVES &
ACHIEVEMENTS DURING 2005-06
Ø
Registered a net profit of Rs. 701
crore in the year 2005-06.
Ø Achieved
an all time high sales turnover of Rs. 1834 crore as against Rs.
1668 crore during the year 2004-05
Ø
Rs. 140 crore given to
Government of India as Dividend for 2005-06.
Ø Highest
rating for Domestic borrowings i.e. ‘AAA’ & for external
borrowings BB+/Stable, equivalent to Sovereign rating
re-affirmed by reputed International rating agencies.
Ø The
average rate of Interest on borrowings has been brought down to
around 6% p.a. (2005-06) from 10% p.a. (1999-2000)
Ø The
Corporation is in the process of raising 100 Million USD loan
through ECA route for part financing of prestigious Subansiri
lower Project.
Ø As
financial re-engineering General purpose loans raised in
previous years (1997-98 to 2002-03) are being pre-paid to
improve profitability, Corporation is poised to liquidate all
General purpose loans during the current financial year.
Ø Became
self sufficient for its short term/ working capital needs.
Ø Standardized
Accounting & Internal Audit procedures by way of their
Manualisation.
Ø All
set to generate Internal Resources to partly finance funds for
Plan Outlay requirements from the year 2006-07 & onwards.
Ø The
Corporation has switched over to electronic mode of payments to
its contractors/suppliers wherever possible. Some of the
Regional offices have also been lined to net banking.
Paid Up Capital
The Board of NHPC has allotted 5,66,800
equity shares to the President of India in its meeting held on
24.3.2006. With this, the total paid up capital of the
Corporation has gone up to Rs. 10, 215.28 crore.
Power Generation
During the
period under review, the operating Power Stations of the
Corporation generated 12567.15 million units against the MoU
target of 12344 million units for “very good” rating , as
compared to 11286.43 million units generated during the previous
year showing an increase of 11.347 %.
· The
machine availability of the operating Power Stations measured as
capacity index is 98.16 % against the annual MoU target of 96.2
% for Excellent Rating.
· Almost
all power stations exceeded generation target. The 690 MW Salal
Power Station generated 3480.86 million units against the MoU
target of 3082 million units . The 105 MW Loktak Power Station
in Manipur achieved generation of 586.12 million units against
the target of 448 million units. The 60 MW Rangit Power Station
in Sikkim achieved generation of 352.05 million units against
the target of 339 million units. The 180 MW Baira Siul Power
Station in Himachal Pradesh achieved a generation of 790.99
million units against the target of 779 million units. 540 MW
Chamera Stage-I generated 2343.18 million units against the
target of 1665 million units. The 120 MW Tanakpur Power
Station generated 483.15 million units against the target of
452 million units.
Sale of energy & Realization
·
During the financial year 2005-06, the Corporation
raised a total billing of Rs. 1858.27 crore to the various
beneficiaries and the total amount realized was Rs. 1911.32
core. The current outstanding dues towards principal amount have
been reduced to Rs. 20.75 crore ( as on 31.3.2006) from Rs.
73.80 crore ( as on 31.3.2005) which is equivalent to reduction
in terms of months of average billing from 0.54 to 0.13. Besides
the above realization, UI charges of Rs. 58.77 crore and
surcharge of Rs. 22.75 crore and interest on bonds of Rs. 257.14
crore has also been received during the year. Long pending
outstanding dues as on 30.9.2001 amounting to Rs. 33.38 crore
have been securitized into power bonds in respect of Bihar ( Rs.
19.70 crore) and Jharkhand ( Rs. 14.31 crore). Doubtful debts
reduced to Rs. 74.11 crore from Rs. 76.86 crore through
settlement and recovery thereof from the concerned
beneficiaries.
·
The Corporation has signed Power Purchase
Agreement (PPA) for the 330 MW Kishanganga, 45 MW Nimmo Bazgo,
44 MW Chutak, 240 MW Uri-II , 390 MW Dul Hasti , 231 MW
Chamera-III and 160 MW Teesta Low Dam –IV Projects with the
concerned beneficiaries of Northern and Eastern Region.
Project commissioned
· The 280 MW Dhauliganga Power Station in
Pithorgarh District of Uttaranchal started commercial operation
with effect from 01.11.2005 . Power from this Power Station is
being sold at a provisional rate of 183 paise per unit as
approved by CERC. The beneficiary States are Uttaranchal,
Haryana, Chandigarh, Himachal Pradesh, Jammu & Kashmir,
Punjab,Rajasthan, Uttar Pradesh and Delhi.
·
The Dhauliganga Power Station was dedicated to the
Nation on 8.4.2006 by Shri Sushilkumar Shinde, Hon’ble Union
Minister of Power.
Capacity
Addition
·
Xth Five Year Plan 2480 MW (See Annexure I)
·
XIth Five Year Plan 6297 MW (See Annexure II)
Projects under construction
·
Teesta Stage-V (510 MW), Sikkim
Ø
Completed heading excavation of face-III and
Face-IV and benching of Face-II of Head Race Tunnel.
Ø
About 8.20 km. overt lining achieved during the
year.
Ø Assembly of Stators of Unit –I & II , Turbine
Unit-I , Generator of Unit-II completed. Assembly of Generator
of Unit-III is in progress. Rotors of Unit-I & II assembled and
lowered.
Ø
During the year 2,60,000 cum. concreting of the
Dam was completed. So far about 3 lakhs cubic meter concreting (
80%) of the Dam has been completed.
·
Dul Hasti ( 390 MW) , Jammu & Kashmir
Ø
Work on the 390 MW Dul Hasti Project is in the
advanced stage.
·
Parbati-II ( 800 MW) , Himachal Pradesh
Ø
Excavation of Adit to Surge Shaft (294 m)
completed.
Ø
Excavation of Head Race Tunnel from Face-II ( 2864
m) completed.
Ø Completed boring of the inclined pressure shaft (
left side). This is the first inclined pressure shaft in the
world having a length of 1546 m and excavated diameter of 4.88
m bored with double shield Tunnel Boring Machine (TBM) followed
by erection of segmental pre-cast concrete lining.
Ø
Completed the excavation of Dam ( 210000 cum) and
started concreting of the Dam.
Ø Carried out 7564 m excavation of Head Race Tunnel.
Record progress of 1000m excavation achieved during April 2005.
Ø
The total tunneling achieved up to 30.3.2006 is
over 11497 m
·
Parbati-III ( 520 MW) , Himachal Pradesh
Ø
Obtained Environment and Forest clearance from
Ministry of Environment & Forests, Government of India
Ø
CCEA approval accorded by Government of India
Ø Consent to establish the project was granted by
Himachal Pradesh State Environment and Pollution Control Board.
Ø Contract Agreement for award of major civil
works under Lot-I - construction of Diversion cum Spillway
Tunnel including gates and hoists, Coffer Dams, Rockfill Dam,
Spillway, Intake Structures and Head Race Tunnel finalized on
15.12.2005.
Ø Contract Agreement for award of major civil works
under Lot-II - Construction of part Head Race Tunnel, Surge
Shaft, Pressure Shaft, Power House and Tail Race Tunnel
finalized on 15.12.2005
Ø
Major contractors for Lot-I and Lot-II have
started the work.
·
Subansiri Lower ( 2000 MW) , Arunachal Pradesh
Ø
Excavation of all the five Diversion Tunnels taken
up simultaneously and the work is progressing.
Ø
Excavation of Adit to Pressure Shaft, Surge
Chamber and Power House is in progress.
Ø
Completed the high level road to Dam top .
Ø
River diversion work is progressing satisfactorily
and is expected to achieve River Diversion by October, 2007.
·
Teesta Low Dam-III ( 132 MW) , West Bengal
Ø
Achieved second stage diversion of Teesta River.
Ø
Construction of Coffer Dykes (upstream and
downstream) completed.
·
Teesta Low Dam-IV ( 160 MW), West Bengal
Ø Compliance Report for diversion of forest land for
the project has been forwarded by the Forest Department,
Government of West Bengal to Ministry of Environment and
Forests, Govt. of India.
·
Sewa-II ( 120MW) , Jammu & Kashmir
Ø
Excavation of Adit to Desilting Chamber / Gate
Operation Chamber completed.
Ø
Excavation of upper horizontal Pressure Shaft from
Valve House end completed one month ahead of schedule
Ø
Excavation of Dam foundation and Adit to Surge
Shaft bottom completed.
Ø
Excavation of pilot hole in Surge Shaft completed.
Ø
4830 m (approx.48%) excavation of Head Race Tunnel
completed.
Ø
Concreting of Dam is in progress. Approximate
15000 cum. concreting placed so far.
·
Chamera-III ( 231 MW), Himachal Pradesh
Ø
Started construction of Adit-III, Adit-IV, DT
inlet and outlet, ventilation tunnel and main access Tunnel.
Ø
Completed construction of Gehra Bridge and
Durgethi Bridge on Ravi River.
Projects under construction on
Turnkey Basis
·
Sippi ( 4 MW), & Kambang (6 MW) Arunachal
Pradesh
Ø
NHPC has taken up for construction the Sippi and
Kambang Projects in Arunacahal Pradesh as a deposit work.
Ø
90 % the works of Trench Weir intake, Silt
Flushing Channel, Setting Basin, Forebay and Power House and 70%
works of Power Channel have been completed.
Ø
Work on the Kambang Project is also progressing
well.
Consultancy Services
-
NHPC has been providing consultancy
services in the area of Hydro Power development for
generating additional revenue for the Corporation in the
form of consultancy business. The clients to whom the
consultancy services are being provided include agencies /
organizations both in public and in private sector in India
and abroad.
-
During the Financial Year 2005-2006
consultancy assignments amounting to Rs. 65.26 crore and
total payment amounting to Rs. 15.04 crore were received.
-
NHPC is registered as a “Consultant”
with World Bank, Asian Development Bank, African Development
Bank and Kuwait Fund for Arab Economic Development. The
Corporation is also registered as a Consulting Agency with
Central Water Commission and Consultancy Development Centre.
-
The Corporation has signed number of
MOUs with various organizations for providing Consultancy
Services which includes MOU signed with M/s. Lahmeyer
International GmbH, Germany and JSC “ Centre of Engineering
UESR” Institute Hydroproject Moscow, Russia for mutual
collaboration for providing consultancy and management
services for consultancy and turnkey project execution in
the field of hydro power plants and associated structures in
India and other countries.
Rural Roads Project
-
Under the Pradhan Mantri Gram Sarak
Yojana (PMGSY) NHPC has undertaken construction of Rural
roads in East Champaran, West Champaran, Muzzafarpur,
Vaishali, Sitamarhi and Sheohar Districts of Bihar.
Accordingly, tripartite agreement amongst NHPC, Rural
Development Department, Government of Bihar and Ministry of
Rural Development, Government of India has been entered
into.
-
As on today 59 roads of 445 Kms. with
a cost of Rs.183 Crore have been cleared by Ministry of
Rural Development, Government of India.
-
Works on 43 roads with a total length
of 343 Kms. with an estimated cost of Rs.136 Crore have been
taken up and is expected to be completed by the end of
December 2006.
-
Tender proceedings to award 16 roads
covering 112 Kms. are under process.
Rural Electrification Projects
-
Under Rajiv Gandhi Gramin Vidyutikaran
Yojana (RGGVY), NHPC has taken up Rural Electrification
works in East Champaran, West Champaran, Sitamarhi, Sheohar,
Darbhanga and Madhubani districts of Bihar. Detailed
project reports of Rural Electrification works of all the
six districts are under finalization.
The Corporation has also taken up rural
electrification works in Purulia District of West Bengal and in
state of Chattisgarh.
Research and Development
Activities
-
NHPC is a participating agency in
conjunction with IITs and CPRI Bangalore in the National R&D
Project for development of silt resistant material for
elongation of service life of underwater components for
which National Metallurgical Laboratory, Jamshedpur is the
lead agency. The proposal has been approved by the Standing
Committee of Government of India on R&D.
-
Being the Nodal agency for exploration
of geo-thermal energy, NHPC has carried out ranking studies
and identified six most promising geo-thermal fields in
India, which are Tatta Pani in Chattisgarh, Puga in J&K, Cambey Graben in Gujarat, Manikaran in H.P., Surajkund in
Jharkhand and Chhumathangi in J&K.
-
A pilot project for adoption of
solar energy at Nimmo Bazgo Hydroelectric Project (Leh)
of NHPC Investigation Schemes is being undertaken to promote
green power and likely to be commissioned in 2006-07.
Major Contracts Awarded
-
Lot 1 of civil works package of 240
MW Uri-II Project to M/s. Hindustan Construction Company
Ltd. at a cost of Rs. 574.99 crore
-
Major civil works of 231 MW Chamera
Stage-III to M/s. Hindustan Construction Company Ltd at a
cost of Rs. 504.87 crore.
-
Lot 1 of civil works package of 520
MW Parbati Stage -III Project to M/s. Patel – L&T Consortium
at a cost of Rs. 439.08 crore and Lot-2 of civil works
package to M/s. Jager – Gammon JV at a cost of Rs. 324.20
crore.
-
Civil works packages of 160 MW Teesta
Low Dam-IV Project to M/s. Hindustan Construction Company
Ltd. at a cost of Rs. 395.90 crore.
Recently approved projects by
CCEA
During the period under review CCEA
clearance for the following projects were received
-
231 MW Chamera-III ( Himachal
Pradesh)
-
520 MW Parbati –III ( Himachal Pradesh
)
-
160 MW Teesta Low Dam -IV ( West
Bengal )
-
240 MW Uri-II ( Jammu & Kashmir )
New Projects
The following projects were entrusted to
NHPC for execution by the Government of Uttaranchal and
Government of Sikkim:
-
240 MW Chungar Chal ( Uttarnchal)
-
630 MW Garba Tawaghat ( Uttaranchal )
-
55 MW Karmoli Lumti Tulli (
Uttaranchal )
-
495 MW Teesta Stage-IV ( Sikkim )
-
210MW Lachen ( Sikkim )
Status of other Projects
-
1000 MW Pakal Dul in J&K – DPR
submitted to CEA/ CWC for TEA
-
3000 MW Dibang Multi Purpose Project
in Arunachal Pradesh - DPR submitted to CEA/ CWC for TEC
-
195 MW Kotli Bhel –I A in Uttaranchal
- DPR submitted to CEA/ CWC for TEC
-
320 MW Kotli Bhel – I B in Uttaranchal
- DPR submitted to CEA/ CWC for TEC
-
530 MW Kotli Bhel – II in Uttaranhcal
- DPR submitted to CEA/ CWC for TEC
-
420 MW Lakhwaar Vyasi in Uttaranchal -
DPR submitted to CEA/ CWC for TEC
-
20 MW Bav-II in Maharashtra - DPR
submitted to CEA/ CWC for TEC
-
600 MW Kiru in Jammu & Kashmir - DPR
submitted to CEA/ CWC for TEC
-
330 MW Kishenganga Project in J & K –
TEA accorded to the revised proposal by CEA.
Enterprise Resource Planning (ERP)
The huge targets and challenges of NHPC to
add more than 30,000 MW of hydropower capacity in next 15 years
shall require organizational transformation and information
technology is considered as an important enabling tool to
achieve the same. It is in this context, that the organization
has launched a major initiative to implement Enterprise Resource
Planning (ERP) software solution framework.
The ERP solutions shall enable integrating
major business processes of NHPC to achieve quality of work,
improved profitability and performance. ERP systems shall also
provide opportunities to the organizations to adopt global best
practices. Ernst and Young, a world renowned Consulting
Organization has been engaged as Consultant for the Project.
The ERP initiative in the organization has been given the name
‘Project Kiran’ which was formally launched by Shri S.K. Garg,
CMD, NHPC on 13th January 2006.
Social responsibility
-
NHPC has implemented number of welfare
measures for the benefit of the people living in and around
its Power Stations and Projects. The Corporation undertook
large-scale relief operations in the earthquake hit Jammu &
Kashmir State. The Corporation donated Diesel Generating
sets, provided medicines, drinking water, food items, woolen
blankets, sweaters, shawl, tents, construction material etc.
to the victims of earthquake.
-
NHPC employees contributed one day
salary amounting to Rs. 68,93,827/- to the Hon’ble Prime
Ministers National Relief Fund for providing relief to the
victims of the earthquake.
Joint Venture Projects
-
Narmada Hydroelectric Development
Corporation (NHDC)
Narmada Hydroelectric Development
Corporation is a Joint Venture of NHPC and
Madhya Pradesh Government. The two Projects of NHDC are the
1000 MW Indira Sagar and 520 MW Omkareshwar .
Ø
Indira Sagar Project (1000 MW)
Indira Sagar Project with 8 units of 125
MW each was completed in March 2005. The design energy of this
project is 1980 million units. The Project has achieved the most
important milestone by commissioning the last unit (Unit No: 8)
on 30th March, 2005 two months ahead of sanctioned
schedule and has provided 4070 million units of electricity so
far to the power deficit State of Madhya Pradesh at relatively
much cheaper rates resulting in substantial savings for the
state also. The estimated cost of the project was Rs. 4355.57
crore at September 2000 Price level, but Project has been
completed at lesser cost earning reputation of being rare
project for achieving this feat.
Ø
Omkareshwar Project (520 MW)
The 520 MW Omkareshwar Project with 8
units of 65 MW each is designed to generate 1166 million units
annually. CCEA has accorded approval for the execution of the
Project by NHDC by February 2008. The work of the Project has
been awarded to a consortium of M/s Jai Prakash Voith Siemens
for execution on turnkey basis and the project is scheduled to
be completed within less than 4 years by October 2007. Work on
the project is progressing fast with achieving a record
highest concreting of 1.3 lac cu. mtr. in the month of
March,2006.
|